Approval of a new methodology

A new methodology goes from synopsis to full document, 30 days of public consultation, assessment by two independent VVBs and a final NCCF review before it is listed.

MethodologiesLast reviewed 23 October 2026

Steps

StepWhoWhatTime
1IMDSubmit a synopsis on the template and pay the fee
2NCCFReview the synopsis: approve, ask for one revision, or reject14 working days
3IMDSubmit the methodology document and pay the fee
4NCCFCheck completeness and consistency7 working days
5PublicExtended stakeholder consultation; the IMD responds to comments30 days
6IMD, VVB 1Appoint the first VVB, which assesses the methodology
7NCCFReview the first assessment report14 working days
8NCCF, IMD, VVB 2NCCF appoints a second VVB; the IMD contracts and pays it
9NCCFReview the second assessment report21 working days
10IMD, both VVBsAlign both reports with the final methodology
11NCCFFinal review of the approval request21 working days
12NCCFList the methodology with a reference number5 working days

Review times exclude the time taken by the IMD or VVB to respond.

LCA-based methodologies, introduced in Carbon Standard v1.1, are not assessed by VVBs. See Which methodologies can be used?

Grounds for refusal

Either VVB does not approve; the methodology doesn’t comply with the Carbon Standard or the Validation and Verification Standard; its quality is below NCCF’s benchmarks; or it conflicts with the Registry’s philosophy or integrity.

Fees are not refunded on rejection. Methodology fees are on Methodology fees and compensation.

Withdrawing an approved methodology

The IMD can request withdrawal at any time, with reasons. NCCF reviews it within 14 working days after outstanding dues are cleared.